Engineering · L3 · Treehouse Project — Task Dependencies & Critical Path

The treehouse example's task dependency chain, with the critical-path tasks highlighted — the longest chain that sets the shortest possible project time.

Engineering
Updated
0
0
Read only
🧾 Buy materials — 2dCut wood — 1dAssemble frame — 3dAdd roof — 1d🎨 Paint treehouse — 1dBuy paint — 1d